- October 14, 2021
- Projects
The Chase West project is officially midway.
Work on the 3.3-kilometre expansion of the Trans-Canada highway, west of Chase, B.C., is roughly halfway complete. To date, Dawson Civil has excavated and placed nearly 500,000 cubic metres of material and installed 1.5 kilometres of pipe - varying in size from 20 centimetres, u