Project: Highway 1 Chase Creek Road to Chase West

Traffic delays on Highways No. 1 and Shuswap Ave. can be expected due to road construction activities. Construction activities to consist of:

Daytime blasting is scheduled for November 16th to November 30th, which will result in 20 minute road closures. Blasts will occur between 9:00am – 3:00pm.

Nighttime Blasting is tentatively scheduled for December 1st which will result in 45 minute road closures. Blasts will occur between 11:00pm – 5:00am.

Prior to each blast, a sweep of the affected area shall be conducted to ensure that no members of the public are present.

Blasts will be signaled by 12 “toots” on an air horn 2 minutes prior to each blast. One long “toot” on the air horn will signal that the blasting is all clear. Minor vibrations from this operation should be expected.

Updates will be posted to DriveBC.ca, Facebook and Twitter.

If you have any questions, concerns or require further information, please contact 250-682-1512.